Friday, January 23, 2009

Moving Moving Moving.

We are about 6 months late with this post. The finsh carpenter came and completed the bamboo stair railing and false tread ends, using most of the pieces Ohm's Mom had stained and varnished. We then spent quite a bit of time cleaning, and getting ready to move.
We were glad to see the port - a -potty being hauled off.

The day before moving, the carpet installer came out and put in all of the carpet. He put in the pad and laid out the carpet up stairs. He then ran out of time for the day. After promising to be finished by noon of Moving Day, he went home.
Sure enough, by noon the next day he was finished.
With about an hour to spare before the truck arrived.
Thanks to Jason, Matt, Marcos, Aunty, and Lonnie for the moving help.Although everything was not quite complete yet, we were glad to be back home. We had been out of the house a little over five months and added about 1000 square feet in this little adventure.

Over the next few months, we slowly finished everything else. We have really appreciated the extra space. Ohm had a lot of company over Thanksgiving. There was a total of 17 people staying at the house. While it was a little crowded, we were able to manage without too much loss of sanity. The extra play area has also been handy for getting Ohm's toys out of the downstairs living area. It will also come in handy in a couple months when Ohm's baby sister arrives.
But that should be the topic of a new blog.

Tuesday, May 13, 2008

Home Stretch

Most of the work is complete and we will be moving back home soon. All of the walls and most of the trim are painted, with help from Auntie and friends. Even Ohm wanted to help out with painting.

The electrician came out and did the final electrical trim out. He put in all the switches outlets and lights.

In preparation for the trim, we removed all the boards we put down back in December to protect the floors.

We were worried about the condition of the floors under the boards. They survived fairly well. There were a couple spots of mold in areas where water made it under the plastic sheeting. The most of the mold came off with some bleach water. We will try vinegar on the leftover mold spots

The finish carpenter came out and put in all the trim and made the bench.

The finish carpenter also installed the bathroom vanity. We installed the counter top (which we ordered online).The tile installer put in the shower and the backsplash in the kitchen.

The forms are up for the front and back steps.

We are having bamboo stair pieces installed to match the downstairs floors. We ordered caramelized bamboo pieces, but when it arrived, it appeared to be uncaramelized. Ohm's Mom stained all the parts at the last minute so they would be ready for installing today.

The concrete will be poured tomorrow. On Thursday and Friday we will install carpet. This weekend we will start moving back home!

Sunday, April 20, 2008

Siding and Piles

We got rid of one pile and created another.

Since the framer finished his work, we got all of the unused lumber together and put it on our RV parking. The lumber company came by on Monday the April 7 and picked it up. We will get a refund from them for our left over lumber.

The house also got its siding in the last couple weeks. They started installing the siding on the 4th. It took a little over a week for the installation portion to be complete. They finished up last Monday.

By Wednesday the painters had started in on the exterior.

After the first day of painting, we were a little worried that it looked too yellow. By the time it finished drying, and the trim was painted, the house looked a bit less yellow.
The siding company will be hauling off their pile in the next few days.

The only things left for the exterior are to add a concrete step out the front and back door, and for the lighting to be installed.

The interior has been moving along as well. The drywall is complete. For painting, we hired painters to paint all of the ceilings, the stairwell area and the main area downstairs. Ohm's aunt is in charge of painting the rest. The painters finished their portion on Friday. We now have enough complete for the finish carpenter to start his work tomorrow morning.

Wednesday, April 2, 2008

Drywalling begins

It was quite the happening day today. The drywallers came today and started installing drywall. They should be finished tomorrow with the nailing and we will get the drywall nailing inspection on Friday.

We also had someone come by to haul away our trash pile. It took one and a half truck loads for them to haul it away.

When Ohm's mom stopped by the rental house for lunch, she got word that the siding materials would be delivered in the afternoon, and work on the siding will start tomorrow. To get ready for this, Ohm's dad came home early and removed a couple sections of fence and a trellis that were attached to the house.
We stayed at the house late into the evening getting Ohm's room ready for retexturing and the new windows in the old bedrooms ready for the drywall surround, which will also occur tomorrow.

It feels like we're closing in on the finish line!

Monday, March 31, 2008

Insulation and Heating

The house has insulation and the furnaces are on. We were scheduled to have the insulation installed on Thursday and the insulation inspection Friday morning. Thursday afternoon, Ohm's mom arrived at the house to discover that the insulation installation company had not shown up as scheduled. This is the same company that put the insulation in before they were supposed to. After calling them, and rescheduling the inspector for Friday afternoon, they came out Friday morning to reinstall the insulation. The inspector passed the insulation, fire blocking and extra nailing.We have also started using the furnaces over at the house. We had to start it Friday night in anticipation of the drywall delivery Monday morning. It is much nicer working over there with the heat. It feels much warmer than the rental house. The downside is that there is no attic insulation and we are sure that most of our heat is escaping through the roof.

The drywall is now stacked around the house. They will start hanging it tomorrow. The end is in sight!

Wednesday, March 26, 2008

It Passes!!! (almost)

Getting the framing inspections complete has been quite the adventure. We first attempted to pass on Friday, March 7. After have our special hold down testing done (see Solving a Series of Problems) we called for the framing inspection. We were hoping that the inspector would do the interior framing inspection so that we could get started on the drywall upstairs at the same time as finishing the exterior shear wall downstairs. Then we would be on track to move back in by the end of April. But when he came (after Ohm's mom had been waiting at the house with Ohm for almost 2 hours) he said that we needed to have the exterior shear wall installed, and the house exterior wrapped before he would do the framing inspection. This meant coordinating the following sequence of work and inspections before starting any drywall.

1. Put insulation in downstairs exterior walls.
2. Have that insulation inspected.
3. Put the OSB (plywood) on the downstairs exterior walls.
4. Have a shearwall inspection for that.
5. Have all of the exterior OSB (upstairs and downstairs) wrapped with waterproof material.
6. Have the framing inspection.
7. Do any fixes required from the framing inspection (we hear they never pass the first time).
8. Put in the insulation upstairs.
9. Have that insulation inspected.
10. Start drywall!

With this list we sadly realized that we wouldn't be able to move back at the end of April as hoped.

We called the insulation company and told them we needed only downstairs exterior insulation on the first trip. Unfortunately, the company was a little over zealous in their work, and installed all of the interior and exterior insulation. After a few frantic calls, apologies from the insulation company, and a stern note from the inspector that it was not OK to install insulation quite yet, the installation company came out and removed the insulation from the interior. They left it in piles throughout the house for later use.
The next challenge was getting the house wrapped. We hadn't scheduled the exterior siding company yet. The house was ready for the wrap on Monday, March 17. However due to a backlog of work at the siding company, they told us that they would be able to get to wrapping our house until last weekend. It wasn't until Friday that we realized that it was Easter weekend. By then we had the final framing inspection scheduled for Monday afternoon with the inspector and framer. Ohm's dad was going to take a vacation day from work so Ohm's mom wouldn't have to be there. By 1 PM Sunday we had not seen the siders. Ohm's mom made a call to make sure they were coming, and was assured that they were still planning on coming. By 4 PM, the company president and a helper were out installing wrap on the exposed shear walls. The schedule hiccup was averted and the inspection would continue as planned.At 8:30 Monday morning, Ohm's dad had just delivered Ohm to the babysitter for the day. He was just getting ready to go work at the house when his cell phone rang. It was the city calling. The inspector had called in sick and was unable to make it. After consulting with the framer for his availability, the inspection was reschedule for Tuesday afternoon. Ohm's dad made it into work around 9:30, and rescheduled his vacation for Tuesday.

Tuesday morning at 8:45, Ohm's Dad was getting ready to go over to the house. The city called again and said that the inspector was sick again. After being told that the inspector's back up from another local town was in class all week and checking the framers availability, we rescheduled for Wednesday morning. This time Ohm's mom would attend. Her cell phone number was left with the city as a contact number. She was planning on calling the framer in the morning and asking him to call her when the inspector arrived so that she wouldn't have to wait at the house with Ohm for 2 or 3 hours.

Wednesday morning at 8:45, Ohm's Dad was at work. He received a call on his cell phone from the inspector saying that he was getting ready to head out for inspections. His schedule was packed and he wanted to make sure someone would be at the house. He didn't know when he would be there, but he would be there.

Ohm's dad called Ohm's mom to relay the message. Ohm's mom tried to contact the framer but was unable to get a hold of him. So, she very quickly loaded up Ohm and headed over to the house. When she arrived, she discovered that the framer had been there earlier that morning, but had left. Ohm's mom had no other choice but to wait for the inspector to arrive. Ohm took this opportunity to play in the puddles in the driveway.
The inspector arrived about an hour later. After looking through the house, he requested that some fire blocking be added to a wall over the garage on the second floor, and a few more nails be added to some of the brackets. He gave the OK to install the insulation, and he will sign off on the framing inspection when he performs the insulation inspection.

Not long after the the inspector left, and Ohm's mom had returned to the rental house, the framer called. After arriving at our house this morning, he discovered that his cellphone had died. Rather than wait around, unable to to know if the inspector had called in sick again, he had gone to the Sprint store to get his cellphone fixed. All of the inspectors pickups have been performed, and the house is now ready for the interior insulation to be added tomorrow.

Whew!

Friday, March 21, 2008

Catch Up

Lots has changed since our last picture post. We have all done a lot of work in the house since then.

The framed stairs were added,

The Plummer came out and completed the rough in.

He then informed us that code required that a certain window can't be a type that opens due to the sewer vent just a few feet away.

The chimney was taken down to the floor,

rebuilt through the second floor,

and through the roof.

The HVAC and electrician have been out to do the rough in.

The front gable and bay window have been added,

and the roofers have finished their work, the upstairs windows have been added.
We are currently working in the kitchen putting in a new floor and stripping wall paper. (Sorry, no photos yet)

If all goes well, we will pass the framing inspection on Monday and we will then be able to get the insulation and drywall started.